浜岡原子力発電所1、2号機廃止措置計画認可後の保全について


英字タイトル:
Maintenance program after Approval of Decommissioning Plan of Hamaoka Unit 1 & 2
著者:
湖口 正裕 Masahiro KOGUCHI 中村 雅昭 Masaaki NAKAMURA 清水 義昭 Yoshiaki SHIMIZU 山本 千秋 Chiaki YAMAMOTO
発刊日:
公開日:
カテゴリ: 第7回
キーワードタグ:

概要

Hamaoka Nuclear Power Station got a regulatory approval for a decommissioning plan of Unit 1 & 2 on November 18, 2009. Curre ntly, system decontamination and dismantlement of facilities outside radioactive control area are under process. At the same time, we still have our maintenance program for integrity of required system functions. This paper describes an outline of a revise of maintenance program associated with approval for the decommissioning plan. ywords: decommissioning, maintenance