第16回
保全内容の変更判断をバックアップする数理手法の適用状況調査
著者:
堂﨑 浩二,(日本原電),行則 茂,(東芝ESS),高屋 茂,(JAEA),和地 永嗣,(三菱重工),青木 孝行,(東北大)
発刊日:
公開日:
キーワードタグ:
It is important for maintenance of nuclear power station facilities in the future to promote mathematical techniques which support judgement to modify maintenance practices, such as maintenance tasks, maintenance implementation timing, and so on. Mathematical Maintenance Working Group, which has been established by Maintenance Standardization Committee since July 6, 2018, is investigating application examples of such mathematical techniques in maintenance planning as influence evaluation of changing maint...
英字タイトル:
Investigation on application examples of mathematical techniques to support judgement to modify maintenance practices
第17回
保全遺産第3号 原子力設備の検査用水中遊泳ビークル
著者:
土橋 健太郎,石橋 文彦,上野 聡一,(東芝ESS),今野 隆博,永島 良昭,(日立GE)
発刊日:
公開日:
キーワードタグ:
Underwater inspection vehicles for nuclear power plants were selected as the third maintenance heritage. Hitachi- GE Nuclear Energy, Ltd and Toshiba Energy Systems & Solutions Corporation have been working on miniaturization and weight reduction of vehicles for many years, and enabling visual inspection of narrow space and bottom of the nuclear reactors, which were not accessible with the conventional hanging cameras. This article describes the developed vehicles by each company and their contribution to ma...
英字タイトル:
The Third Maintenance Heritage Underwater Inspection Vehicles for Nuclear Power Plants
第15回
原子力プラントの現場作業を支援するウェアラブルシステム(2)
著者:
尾崎 健司,加藤 貴来,榎本 光広,岡 桂一朗,岩崎 勝郎,伊藤 悠貴,(東芝ESS)
発刊日:
公開日:
キーワードタグ:
The support system which utilized the wearable devices which consist of a smart glass, a camera, a portable computer, a headset, etc., and aimed at the efficiency improvement of field operation was developed. The evaluation results in the actual plant about real time transmission of image and sound between work field and remote office, and the self-localization using VSLAM (Visual Simultaneous Localization and Mapping) technology are reported....
英字タイトル:
Wearable Computing for Support Systems at Work Site of Nuclear Plant(2)
第17回
安全性と経済性を兼ね備えた改良型ABWRの開発
著者:
亀井 一央,(東芝ESS)
発刊日:
公開日:
キーワードタグ:
Toshiba Energy Systems & Solutions Corporation develops improved ABWR which can be implemented in early 2030s. Our development course is that the improved ABWR has both of world highest level safety feature and economic competitiveness against other power generation systems. In safety feature, the improved ABWR introduces passive safety systems for elimination of common caused failure and enhancement of safety reliability, air-cooled ultimate heat sink for reduction of tsunami risk and reinforcement of the ...
英字タイトル:
Development of Improved ABWR with Safety Enhancement and Economic Competitiveness
第17回
巡視点検高度化を目指した映像管理技術開発
著者:
尾崎 健司,坂本 直弥,田副 佑典,渋谷 真人,(東芝ESS),佐野 雄磨,関 晃仁,(東芝)
発刊日:
公開日:
キーワードタグ:
During operation or regular inspections at power plants, regular patrol inspections are carried out in order to identify abnormalities at the site at an early stage. In the patrol inspection, in addition to recording the confirmation items, the site situation is recorded with images such as photographs and videos. It is a process that consumes the administrator's time because it is necessary to manage photos and videos by collating them with the layout of the building. For the purpose of streamlining these ...
英字タイトル:
Development of information management technology for advanced patrol inspection
第17回
巡視点検高度化を目指した移動プラットフォーム開発
著者:
川端 俊一,上田 紘司,笹川 憲二,菅沼 直孝,坂本 直哉,尾崎 健司,渋谷 真人,(東芝ESS),平山 紀之,山下 道夫,(東芝)
発刊日:
公開日:
キーワードタグ:
Due to the increase in aging social infrastructures and the shortage of human resources with the declining birthrate and aging society, labor saving in patrol and inspection work is required. The purpose of this work is not only to reduce the load of patrol and inspection but also to provide new services such as digitization of inspection data. We have developed autonomous four-wheel robot and drone as mobile platforms that can patrol on behalf of workers. The robot can take pictures of the target equipment...
英字タイトル:
Autonomous mobile platform for advanced patrol inspection
第17回
日本保全学会の保全遺産 原子力発電所のピーニングによる 応力腐食割れ抑制技術
著者:
今野 隆博,(日立GE),石橋 文彦,(東芝ESS),沖村 浩司,(三菱重工)
発刊日:
公開日:
キーワードタグ:
The SCC Protect Technology by Peening is registered in The Maintenance Heritage by JSM We introduce The SCC Protect Technology by Peening in NPS...
英字タイトル:
The SCC Protect Technology by Peening in NPS
第16回
監視試験片再生接合技術の実機適用性評価
著者:
田中 重彰,森島 康雄,小川 琢矢,服部 泰大,(東芝ESS),和田 将樹,(日本核燃料開発),神長 貴幸,(東京電力HD)
発刊日:
公開日:
キーワードタグ:
In the application for approval of nuclear power plant operation period extension, it is required to carry out two surveillance tests separately from the conventional plan. At this time, it is necessary to compensate for the surveillance test piece by reconstitution bonding of the used test specimen, since the shortage of the test specimen is expected. Although the used test piece of the welded part is used for the reconstitution bonding of the heat affected zone (HAZ) test piece, the test piece collection ...
英字タイトル:
Applicability of Reconstituted Surveillance Test Piece for RPV Embrittlement Evaluation
第15回
福島第一原子力発電所3号機 使用済燃料プールからの燃料取り出しに向けた環境改善に関する取組み
著者:
小畑 政道,林 弘忠,高橋 純,伊藤 悠貴,(東芝ESS),岡田 伸哉,(鹿島建設),井上 隆史,(鹿島建設),向田 直樹,松岡 一平,(東京電力HD)
発刊日:
公開日:
キーワードタグ:
Removal of large rubble from the roof and walls of the reactor building collapsed due to the hydrogen explosion and dose rate reduction for human workers to begin preparation work shall be accomplished for retrieval of spent fuel from the spent fuel pool at Fukushima Daiichi Nuclear Power Station Unit3. This paper describes the method of survey and evaluation, decontamination and shielding method for dose rate reduction on operational floor of Fukushima Daiichi Nuclear Power Station Unit3....
英字タイトル:
Approach to Dose Rate Reduction for Retrieval of Spent Fuel from Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Unit3
第15回
福島第一原子力発電所3号機 使用済燃料プール貯蔵燃料取出しに向けた取組み
著者:
諏訪薗 司,篠崎 史人,東倉 一郎,小野 剛,(東芝ESS)
発刊日:
公開日:
キーワードタグ:
Since the 2011 Great East Japan Earthquake, Toshiba Energy Systems & Solutions Corp. (Toshiba) has accomplished various tasks in preparation for the upcoming fuel removal operations at the Fukushima Daiichi Nuclear Power Plant (F-1) Unit 3. In November 2015, TEPCO and Toshiba removed large rubble (e.g. Fuel handling machine) that had been sitting inside the spent fuel pool [SFP] as a result of the hydrogen explosion. Currently, Toshiba continues to work on the projects related to fuel removal from the SFP, ...
英字タイトル:
Effort aimed at removal of stored fuels from SFP in Fukushima Daiichi Nuclear Power Station