Hamaoka Nuclear Power Station Unit 1 and 2 have already started the plant decommissioning since November, 2009. The decommissioning Stage-1 (preparation stage) had been already finished and now Stage-2 (Dismantling stage of Reactor Zone Peripheral facilities) is in progress. We have begun a research about material degradation by using some pieces of concrete and metal taken from Unit 1. This report describes the project scheme of the research.